News

West Metro’s new fire safety expert is an experienced engineer and fireman

Mikko Mauro begun work as a fire safety expert in the West Metro project on 25 October. In addition to supervising fire engineering, Mauro will focus on managing fire safety as a whole in the planning, construction and introduction phases of the project.

Mauro transferred to the West Metro from L2 Fire Safety Ltd. He previously worked at L2 as a fire engineer in the West Metro’s Ruohonlahti-Matinkylä phase, so the West Metro is a familiar project for him.

Mauro also has practical experience in rescue work – before his career as a fire engineer, he worked as a fireman. He also holds a Master’s degree in education from the University of Helsinki.

“The metro offers interesting challenges in a professional sense. We are implementing a good, high-quality public transport solution that will serve society in an extensive way”, Mauro says.

 

Board of Länsimetro Oy, summary of decisions – 31 October 2017

A status report on HKL’s introduction of the Ruohonlahti-Matinkylä section was presented to the Board.

The Managing Director was authorised to begin preparations for the procurement of the construction projects of phase two, the Matinkylä-Kivenlahti section.

The Chief Financial Officer of Länsimetro Oy presented the company’s financial situation to the Board. The Managing Director was authorised to begin a tendering exercise and enter into a contract with respect to a maximum of EUR 50 million of financing for the second phase of the Matinkylä-Kivenlahti line.

The company’s measures to develop internal communications in the project organisation for the second phase were presented to the Board.

The next meeting will be held on 17 November.

Further information:

Ville Saksi, CEO, Länsimetro Oy, tel. +358 (0)40 823 2086

Olli Isotalo, Chairman of the Board of Länsimetro Oy, tel. +358 (0)50 593 3359

Media contacts: Satu Linkola,Communications Director, tel. +358 (0)46 877 3392

Ruoholahti-Matinkylä to open for traffic on 18 November

HSL announced on 10 November that the Ruoholahti-Matinkylä section will be opened for passenger traffic on Saturday 18 November.

When traffic starts, HKL will be responsible for operation as well as the servicing and maintenance of the track and stations. Länsimetro will retain ownership of eight stations and the track.

A total of 20,474 workers, hundreds of designers and other experts participated in the construction. Länsimetro thanks everyone involved in the project.

Excavations began from Ruoholahti in 2009.

New electrical expert and scheduling engineer enjoy being on site

The West Metro project has gained two new experts – Juha Kylmänen is starting work as an electrical expert at the Sammalvuori depot and Timo Heiskanen as a scheduling engineer.

Kylmänen, who is from Oulu, has a degree in industrial engineering (B. Eng.) and specialises in machine automation technology.

Metro construction is already familiar to Kylmänen because he was involved in the construction of the Urheilupuisto and Koivusaari stations with his former employer, Amplit Oy. Kylmänen was responsible for completing the electrical work of the stations.

“The special thing about electrical work for the metro is that the supply of electricity is exceptionally well secured. If the primary supply fails, an equivalent system is found immediately”, Kylmänen says.

Kylmänen’s previous work experience includes, for example, working as a maintenance manager at Kontiotuote Oy and as a production and maintenance manager at Pipelife Oy.

“It is nice to look at construction from this side now, as I have a lot of experience from the perspective of a contractor”, Kylmänen says.

The work at the Sammalvuori depot has already shifted from excavation to the construction phase, meaning that Kylmänen’s working days will mainly be spent on site.

“I already visited the site on Monday, and will start serious work on Wednesday. My work largely consists of supervision and instruction”, Kylmänen says.

Gas pipes, mines, nuclear power – and now the metro

Timo Heiskanen is a trained civil engineer, developer, and also holds an MBA from Aalto University (Master of Business Administration).

Previously, Heiskanen worked in his own company from 2014 onwards. His clients included, for example, Baltic Connector Oy, involving him in the construction project of a gas pipeline between Finland and Estonia. He also has experience in the same field from Pori LNG and the construction of an LNG refuelling station, as well as from the Olkiluoto nuclear power plant. Heiskanen has also worked in Australia where he initially went as a backpacker, but ended up getting a job in his own field at Leighton Contractors. Recently, he has been working in a start-up company.

The West Metro as a project offers a view to the new construction sector.

“Since I have already worked on nuclear power plants, mines and gas pipes, I thought that now it would the metro’s turn”, Heiskanen says.

Heiskanen is responsible for the schedule monitoring and management of the second phase project.

“it is important to maintain an up-to-date situational picture. Every day you have to know what is going on – in terms of design, procurement as well as the site”, Heiskanen says.

After the first working days, Heiskanen feels positive and enthusiastic.

“I would like to visit the site already”, he says.

Excavation of Espoonlahdentori entrance to begin at Espoonlahti – excavation of the station continues until end of year

Excavation of the Espoonlahdentori entrance will begin during week 40 at the Espoonlahti worksite on the Matinkylä–Kivenlahti section of the West Metro. Espoonlahdentori will be one of two entrances to the coming Espoonlahti station.

Excavation of the shaft will begin on Monday, 2 October with drilling work, and blasting work is set to commence during the same week. In Espoonlahdentori, the excavation work is carried out on weekdays between 7 a.m. and 6 p.m. The excavation and reinforcement work of the shaft will last for approximately two months.

In Espoonlahti, excavation of the station also continues: this is carried out between 7 a.m. and 10 p.m., with work on the site set to continue until the end of 2017.

The working hours are based on a noise permit by Espoo Environment Department.

Further information: Länsimetro feedback phone number (Mon–Fri 9.00–15.00), +358 (0)50 377 3700

24-hour hotline for the Espoonlahti site: +358 (0)40 637 5377

Second-phase tunnelling work progresses – new breakthrough between Soukka and Espoonlahti rail lines

On 4 October, a new connection between the Soukka and Espoonlahti rail tunnels was excavated on the Matinkylä–Kivenlahti section of the West Metro. In each West Metro contract, the worksites excavate simultaneous tunnels which are then connected at the boundary between contract areas.

Earlier breakthroughs have been made between Finnoo–Kaitaa and Kaitaa–Soukka. After Wednesday’s breakthrough, the tunnel line now runs without interruptions from Finnoo, the first station of the metro’s second phase, to the penultimate station Espoonlahti. The breakthrough between Espoonlahti and Kivenlahti is yet to be accomplished. However, a connection has been excavated between Espoonlahti and the Sammalvuori depot.

The breakthrough was made on 4 October at 7 a.m. The excavation removed some 150 tonnes of rock separating the two tunnels.

A total of 91.3% of the excavations for the West Metro’s Matinkylä–Kivenlahti section are now completed. The excavations will be followed by a construction phase that has already begun in Sammalvuori.

Further information: Länsimetro feedback phone number (Mon–Fri 9:00–15:00): +358 50 377 3700

West Metro occupational safety award granted to Lemminkäinen Infra Oy – “This worksite has the right attitude”

Lemminkäinen Infra Oy, the excavator contractor at Finnoo site, has been named the West Metro’s Safest worksite. The review period of the internal competition was from 1 January to 30 June 2017. The competition is organised semi-annually and its participants are all current West Metro worksites. The prize is a gilded piece of rail track, engraved with the name of the winning contractor.

The award is granted on the basis of accident frequency monitoring and civil engineering worksite safety level (MVR) measurements. MVR measurements are carried out weekly on sites to measure different factors affecting safety, such as worksite cleanliness, condition of machinery and equipment, storage facilities, and protective equipment. The worksite with the best ranking scores in accident frequency monitoring and MVR measurements is named the winner. MVR results are given a weight of 80% in the ranking, while accident frequency monitoring carries a weight of 20%.

“This worksite has always held the right attitude – safety requirements are complied with not just due to rules, but over a real concern for employees. Any flaws are addressed without delay,” says Tiia Virtanen, Safety Coordinator for the West Metro project.

This is not the first time Lemminkäinen Infra Oy has won the award for safest worksite: the company is a two-time winner from West Metro excavation contracts and earned one award for the construction project of the Ruoholahti–Matinkylä section of the line.

“It always feels good to get recognition such as this. It shows that we have been doing things the correct way. A culture of safety is important to us. It means that people can carry out their tasks safely and leave work healthy,” says Markku Okkonen, Site Manager for the Finnoo excavation project.

Commercial construction expert to join as project engineer in Espoonlahti

Patrik Kalteva (B. Eng.) began work at the West Metro as a project engineer on 9 October. Kalteva will join the West Metro section of Matinkylä–Kivenlahti as a project engineer in Espoonlahti.

Kalteva transferred to the West Metro project from his position in NCC as site manager and quality engineer. Kalteva took part in, for example, the construction of the Matinkylä metro station, and has experience from the renovation of business premises at Fazer and the construction of the Alberga Business Park. At Consti Group, Kalteva worked as a chief supervisor in pipe renovation projects.

On his first day, Kalteva is eager to begin work at West Metro.

“This opportunity was too good to pass. I look forward to being a part of such a unique and extensive project, as well as taking responsibility for more large-scale assignments,” Kalteva says.

Board of Länsimetro Oy, summary of decisions – 10 October 2017

The Board discussed the contents of the partnership agreement between Länsimetro Oy and HKL. Länsimetro Oy has handed over control of the rail and stations and their technical systems to the management, responsibility and maintenance of HKL by an agreement signed on 3 October. Ownership shall remain with Länsimetro Oy, and management in accordance with the articles of association with its shareholders. In the agreement, HKL is tasked with the same duties concerning the rail, stations and systems of the West Metro as in the case of the existing metro line. HKL is responsible for the responsibilities and safety management system in accordance with legislation on urban rail transit.

The Board received a status update on the comprehensive safety and risk management of the Martinkylä–Kivenlahti section of the West Metro.

The next meeting will be held on 31 October.

Further information:

Ville Saksi, CEO, Länsimetro Oy, tel. +358 (0)40 823 2086

Olli Isotalo, Chairman of the Board of Länsimetro Oy, tel. +358 (0)50 593 3359

Media contacts: Satu Linkola,Communications Director, tel. +358 (0)46 877 3392

Come hear about the metro construction – discussion session on the Matinkylä–Kivenlahti section on 23 October.

The West Metro project holds monthly discussion and info sessions on the progress of the project. The next session is held on Monday, 23 October, from 3 p.m. to 6 p.m. at Soukka library, at the address Soukantie 4.

The info sessions, held along the Matinkylä–Kivenlahti section, present the opportunity to ask questions and discuss matters related especially to the progress and construction of the second phase of the West Metro. The session will answer questions on, for example, the type of excavation work carried out and any construction work taking place near your home.

Excavations for the Matinkylä–Kivenlahti section are nearing completion: 91.6% of the required total is now ready.

Further information: Länsimetro feedback phone number (Mon–Fri 9.00–15.00), +358 (0)50 377 3700