Board of Länsimetro Oy, summary of decisions – 31 October 2017

A status report on HKL’s introduction of the Ruohonlahti-Matinkylä section was presented to the Board.

The Managing Director was authorised to begin preparations for the procurement of the construction projects of phase two, the Matinkylä-Kivenlahti section.

The Chief Financial Officer of Länsimetro Oy presented the company’s financial situation to the Board. The Managing Director was authorised to begin a tendering exercise and enter into a contract with respect to a maximum of EUR 50 million of financing for the second phase of the Matinkylä-Kivenlahti line.

The company’s measures to develop internal communications in the project organisation for the second phase were presented to the Board.

The next meeting will be held on 17 November.

Further information:

Ville Saksi, CEO, Länsimetro Oy, tel. +358 (0)40 823 2086

Olli Isotalo, Chairman of the Board of Länsimetro Oy, tel. +358 (0)50 593 3359

Media contacts: Satu Linkola,Communications Director, tel. +358 (0)46 877 3392