Board of Länsimetro Oy, summary of decisions – 20 December 2017

The Managing Director presented the purchase schedule for the forthcoming Matinkylä-Kivenlahti building contracts. The procurement notice for the rail line contract was submitted to HILMA (the electronic procurement notice system maintained by the Ministry of Economic Affairs and Employment) on 15 December. Tendering for the remaining building contracts will take place during spring 2018.

The competitively tendered framework agreements for construction expert services were presented to the Board. According to the framework agreement, expert services in the fields of construction, building services, track engineering and measurements will be procured from a total of 17 different suppliers.

The situation management model for the second phase was presented to the Board.

The Board received a status update on the comprehensive safety and risk management of the second phase.

Further information:

Ville Saksi, CEO, Länsimetro Oy, tel. +358 (0)40 823 2086

Olli Isotalo, Chairman of the Board of Länsimetro Oy, tel. +358 (0)50 593 3359

Media contacts: Satu Linkola,Communications Director, tel. +358 (0)46 877 3392

Rescue exercise to be arranged at the Kaitaa excavation site on 12 December

Länsi-Uusimaa Department for Rescue Services will arrange a rescue exercise at the Länsimetro excavation site in Kaitaa at Kaitaantie 6 on Monday 12 December 2017, starting from 13:00.

This exercise will last for around two hours. A fire or an electrical fire was selected as the fictional scenario of the accident. The participants will include SRV Infra Oy, which is the contractor at the Kaitaa excavation site, the rescue department of Länsi-Uusimaa, and the West Metro project. Two rescue units from the rescue department of Länsi-Uusimaa will participate in the exercise. There will be personnel near the exercise area to direct traffic for the whole duration of the exercise.

This exercise is the ninth rescue exercise in a series of exercises arranged along the track section between Matinkylä and Kivenlahti. During the exercise, personnel of the rescue department will have an opportunity to get familiar with the conditions in underground premises during construction and excavation.

Further information on the exercise

Janne Räsänen, Fire Chief, Länsi-Uusimaa Rescue Department. +358 (0)50 329 8949

Satu Linkola, Communications Manager, the West Metro project, tel. +358 (0)46 877 3392

Rescue exercise to be arranged at the Finnoo excavation site on 11 December

Länsi-Uusimaa Department for Rescue Services will arrange a rescue exercise at the Länsimetro excavation site in Finnoo at Finnoonsilta 9 on Monday 11 December 2017, starting from 13:00.

This exercise will last for around an hour. A fire or an electrical fire was selected as the fictional scenario of the accident. The participants will include Lemminkäinen Oy, which is the contractor at the Finnoo excavation site, the rescue department of Länsi-Uusimaa, and the West Metro project. Two rescue units from the rescue department of Länsi-Uusimaa will participate in the exercise. In the vicinity of the exercise area, personnel will be reserved to direct traffic for the duration of the exercise.

This exercise is the eight rescue exercise in a series of exercises arranged along the track section between Matinkylä and Kivenlahti. During the exercise, personnel of the rescue department will have an opportunity to get familiar with the conditions in underground premises during excavation.

Further information on the exercise

Janne Räsänen, Fire Chief, Länsi-Uusimaa Rescue Department. +358 (0)50 329 8949

Satu Linkola, Communications Manager, the West Metro project, tel. +358 (0)46 877 3392

First and second phase tunnels linked – breakthrough between Matinkylä and Finnoo

The first and second phase tunnels of the West Metro were linked for the first time on Wednesday, 29 November, as a breakthrough was made in the southern rail tunnel, between the completed Matinkylä rail tunnel and the Finnoo tunnel under excavation. The northern rail tunnel will be connected during week 49.

In each West Metro contract, the worksites excavate simultaneous tunnels which are then connected at the boundary between contract areas. At the Matinkylä–Finnoo section, the tunnels were separated by on average a three-metre layer of rock that was removed for the breakthrough.

The breakthrough was carried out so as to not cause disturbance to the operational metro traffic. The breakthrough between the tunnels took place at a distance of some 500 meters from the station. The explosion force was also suppressed by a pressure wall and excavation bank.

After the Matinkylä–Finnoo section, only the Espoonlahti–Kivenlahti section remains unconnected, with the breakthrough between them planned to be carried out in mid-December.

A total of 93.4% of the excavations for the West Metro’s Matinkylä–Kivenlahti section are now completed. Five new metro stations are constructed for the second phase west of Matinkylä: Finnoo, Kaitaa, Soukka, Espoonlahti and Kivenlahti. In addition, an underground metro depot will be constructed in Sammalvuori.

Further information: Länsimetro feedback phone number (Mon–Fri 9:00–15:00): +358 50 377 3700

Riilahdentie shaft excavation work begins at Kaitaa

Excavation of the Riilahdentie entrance to the Matinkylä-Kivenlahti section of the Länsimetro were begun at the Kaitaa work site on week 47. The Riilahdentie shaft is one of the technical shafts of the Kaitaa contract section. Once the metro is completed, these shafts serve as emergency exit, smoke extraction, pressure equalisation and ventilation shafts.

Excavations begun with boring work that will continue for an estimated two weeks. The boring work is followed by blasting work for another estimated two weeks, with the shaft excavation expected to be completed before Christmas.

Both boring and drilling work takes place on weekdays between 7 a.m. and 6 p.m.

Further information: Länsimetro feedback phone number (Mon–Fri 9.00–15.00), +358 (0)50 377 3700

Hotline for the Kaitaa site (24/7): +358 (0)40 183 0090

Excavation at the Suomenlahdentie shaft from 20 November

Shaft excavation will begin at the Suomenlahdentie shaft at the West Metro Finnoo worksite in week 47, from 20 November. Excavation will mainly involve tunnel excavation, as the shaft will be excavated upwards from the tunnel to the ground level. The last blasting at the ground level will involve open excavation.

The blasting work will last about three weeks, followed by reinforcement work and making of the concrete structures. All in all, work on the shaft is expected to be completed in March 2018.

The tunnel excavation will be performed from Monday to Friday between 7 am and 10 pm. The last blasting operation, to be performed as an open excavation, will comply with the working hours specified for open excavation (Mon-Fri 7 am to 6 pm).

What are the shafts? You can find more information on shafts here.

Further information: Länsimetro feedback phone number (Mon–Fri 9.00–15.00), +358 50 377 3700

Finnoo worksite 24-hour hotline: +358 (0)50 421 3344

Excavation at the Maininkitie shaft from 20 November

Excavation of the Maininkitie shaft will begin at the West Metro Espoonlahti worksite on week 47, from 20 November. The Maininkitie shaft is one of the technical shafts of the Espoonlahti contract section. Once the metro is completed, these shafts serve as emergency exit, smoke extraction, pressure equalisation and ventilation shafts.

Excavation of the shaft will begin with drilling of the excavation holes, and blasting work is set to commence after that. The excavation work, which will take approximately three weeks, will be performed on weekdays (Mon-Fri) between 7 am and 6 pm.  The working hours are based on a noise permit by Espoo Environment Centre.

Work at the Espoonlahti worksite also continues at the station, at the Espoonlahdentori entrance and the Opettajantie shaft. The status of the entire worksite is described on the Espoonlahti worksite page.

Further information: West Metro feedback phone number (Mon–Fri 9.00–15.00): +358 50 377 3700

Espoonlahti worksite 24-hour hotline: +358 (0)40 637 5377

West Metro’s new fire safety expert is an experienced engineer and fireman

Mikko Mauro begun work as a fire safety expert in the West Metro project on 25 October. In addition to supervising fire engineering, Mauro will focus on managing fire safety as a whole in the planning, construction and introduction phases of the project.

Mauro transferred to the West Metro from L2 Fire Safety Ltd. He previously worked at L2 as a fire engineer in the West Metro’s Ruohonlahti-Matinkylä phase, so the West Metro is a familiar project for him.

Mauro also has practical experience in rescue work – before his career as a fire engineer, he worked as a fireman. He also holds a Master’s degree in education from the University of Helsinki.

“The metro offers interesting challenges in a professional sense. We are implementing a good, high-quality public transport solution that will serve society in an extensive way”, Mauro says.

 

Board of Länsimetro Oy, summary of decisions – 31 October 2017

A status report on HKL’s introduction of the Ruohonlahti-Matinkylä section was presented to the Board.

The Managing Director was authorised to begin preparations for the procurement of the construction projects of phase two, the Matinkylä-Kivenlahti section.

The Chief Financial Officer of Länsimetro Oy presented the company’s financial situation to the Board. The Managing Director was authorised to begin a tendering exercise and enter into a contract with respect to a maximum of EUR 50 million of financing for the second phase of the Matinkylä-Kivenlahti line.

The company’s measures to develop internal communications in the project organisation for the second phase were presented to the Board.

The next meeting will be held on 17 November.

Further information:

Ville Saksi, CEO, Länsimetro Oy, tel. +358 (0)40 823 2086

Olli Isotalo, Chairman of the Board of Länsimetro Oy, tel. +358 (0)50 593 3359

Media contacts: Satu Linkola,Communications Director, tel. +358 (0)46 877 3392

Ruoholahti-Matinkylä to open for traffic on 18 November

HSL announced on 10 November that the Ruoholahti-Matinkylä section will be opened for passenger traffic on Saturday 18 November.

When traffic starts, HKL will be responsible for operation as well as the servicing and maintenance of the track and stations. Länsimetro will retain ownership of eight stations and the track.

A total of 20,474 workers, hundreds of designers and other experts participated in the construction. Länsimetro thanks everyone involved in the project.

Excavations began from Ruoholahti in 2009.