News

Construction of metro entrances in Soukka

Two entrances will be constructed to the Soukka metro station, one on Soukantori and the other in Yläkartanontie. In connection with the excavation of the Soukantori entrance, a wing of a commercial building at Soukantie 14 will be demolished. The demolition, due to begin in July, is estimated to take four weeks. Another building by the so-called Puotitalo will be demolished in Yläkartanontie. This demolition will begin at a later date, to be announced in due course. The other entrance to Soukka station will be built in Yläkartanontie.

We apologise for any inconvenience caused.

Further information:
Skanska Infra Oy, responsible Site Manager Lauri Harri, lauri.harri(at)skanska.fi, worksite telephone +358 50 560 9092
Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700

Excavation work for Kaitaa metro station and rail tunnels begins

The excavation for the Kaitaa metro station and rail tunnels will begin soon, with SRV Infra Oy as the excavation contractor. The work will begin immediately after the completion of the excavation of the access tunnel in early April. The excavation will include the Kaitaa metro station, 1,600 metres of parallel tunnels, three separate shafts connected to the station and the Hyljetie and Riilahdentie exit shafts.

Working hours at the site, as determined by the Espoo Environment Department, are as follows:
Earthwork and open excavation
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–22.00 and Sat 9.00–18.00)
Tunnel excavation (grout hole drilling, drilling, scaling)
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–7.00 and weekends and mid-week holidays)
Blasting in the tunnel
• Mon–Fri 7.00–22.00 and Sat 9.00–18.00
Loading of excavated rock and transportation
• Mon–Fri 7.00–22.00 and weekends 9.00–22.00 (and if no disturbance is caused to people indoors, also Mon–Fri 22.00–7.00 and weekends and mid-week holidays)

Excavation is estimated to continue until the end of 2017. The monitoring service available on the Länsimetro website shows the rail line and the location of stations and emergency exit shafts. You can also monitor the progress of excavation work at the service.

A briefing for residents will be held at Kaitaa School (Iivisniementie 1) on 5 March at 18.00–19.00, explaining about the project, building site arrangements and excavation.

We apologise for any inconvenience caused.

 

Further information:

Worksite hotline SRV Infra Oy, tel. +358 400 459 827

Site Manager Risto Hast

Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700

Lemminkäinen has won the Finnoo station and rail line excavation contract

Lemminkäinen Infra Oy has won the Finnoo station and rail line excavation contract. Work begins in March 2016, and the contract is due for completion in October 2017. The total contract price is approximately EUR 36 million. In addition to the excavation of Finnoo station and rail tunnels, the contract covers the excavation of a new wastewater tunnel. All in all, 1,380 metres of new metro line and 771 metres of drain tunnels will be excavated.

– The excavation of Soukka and Kivenlahti stations and rail line is in progress. Excavation work is about to begin in Kaitaa and Finnoo and at the underground metro depot in Sammalvuori. Work in Espoonlahti will start later in the spring, says Matti Kokkinen, CEO of Länsimetro Oy.

The section from Matinkylä to Kivenlahti will be seven kilometres long and include the new stations of Finnoo, Kaitaa, Soukka, Espoonlahti and Kivenlahti. In addition, an underground metro depot will be constructed at Sammalvuori. The stretch will be opened to traffic in 2020. Traffic to Matinkylä will begin on 15 August 2016.

Further information:
Matti Kokkinen, CEO, Länsimetro Oy, tel. +358 50 347 1558, matti.kokkinen@lansimetro.fi

Länsimetro Oy is a company jointly owned by the Cities of Espoo and Helsinki, tasked with building the West Metro underground line. The Ruoholahti–Matinkylä section will open to the public in August 2016. Construction of the Matinkylä–Kivenlahti section is under way. This stretch will be completed in 2020.

Seven-year project to be completed in August

The eight stations and 14 kilometres of track to Matinkylä are due to open to the public on 15 August 2016. The excavation and building works have employed approximately 1,500 builders, and the total workload across the project will amount to approximately 4,500 person-years. The final cost estimate for the project is EUR 1,088 million. The project plan gave the cost of the project as EUR 713.6 million (at 2007 prices). Taking into account the rate of inflation, the cost estimate was EUR 848.0 million. The final cost of the project will therefore be EUR 240 million, or 28.3%, higher than planned.

Excavation works began in November 2009. The tunnels had been dug by February 2014, and the tracks had been laid by December 2015. In addition to new stations and two parallel rail tunnels, the project has involved building 15 vertical shafts for emergency exit, ventilation, pressure relief and smoke extraction purposes, nine sets of points, and a total of 54 cross passages between the twin tunnels. Passenger safety is ensured by the underground network’s 52 different automation systems. Safety is further reinforced by systems such as 32 smoke extractors, automatic smoke detection systems, fire extinguisher systems and fire escapes, as well as eight auxiliary power units. All the entrances to the underground are wheelchair accessible. There are a total of 46 lifts and 72 escalators in the underground.

The various systems will be tested independently, per station, and together during the spring. Trains will begin test runs in March. Once the line opens to the public, bus routes that previously terminated in Kamppi will be extended to provide a connecting service to Matinkylä and Tapiola according to a plan drawn up by Helsinki Region Transport. Underground trains will run more frequently than they do now. Two underground lines will be in operation: Matinkylä–Vuosaari and Tapiola–Mellunmäki. At peak times on weekdays, trains will run at 2.5-minute intervals on the section shared by both lines (Tapiola–Itäkeskus). Underground trains currently run at four-minute intervals during peak times.

Further information:
Matti Kokkinen, CEO, Länsimetro Oy, tel. +358 50 347 1558, matti.kokkinen@lansimetro.fi

Länsimetro Oy is a company jointly owned by the Cities of Espoo and Helsinki, tasked with building the West Metro underground line. The Ruoholahti–Matinkylä section will open to the public in August 2016. Construction of the Matinkylä–Kivenlahti section is under way. This stretch will be completed in 2020.

Picture gallery

Excavation work for Finnoo metro station and rail tunnels begins

The excavation for the Finnoo metro station and rail tunnels will begin soon, with Lemminkäinen Infra Oy as the excavation contractor. The work will begin immediately after the completion of the excavation of the access tunnel during March. The excavation will include the Finnoo metro station, 1,350 metres of parallel tunnels, two shafts connected to the station and the Suomenlahdentie shaft.

Additionally, short sections of the sewage tunnels leading to the Blominmäki wastewater treatment plant will be excavated at the same time, for the water services of the Helsinki Region Environmental Services Authority HSY.

Working hours at the site, as determined by the Espoo Environment Department, are as follows:
Earthwork and open excavation
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–22.00 and Sat 9.00–18.00)
Tunnel excavation (grout hole drilling, drilling, scaling)
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–7.00 and weekends and mid-week holidays)
Blasting in the tunnel
• Mon–Fri 7.00–22.00 and Sat 9.00–18.00
Loading of excavated rock and transportation
• Mon–Fri 7.00–22.00 and weekends 9.00–22.00 (and if no disturbance is caused to people indoors, also Mon–Fri 22.00–7.00 and weekends and mid-week holidays)

Excavation is estimated to continue until the end of 2017.

The follow-up service available on the Länsimetro website shows the rail line and the location of stations and emergency exit shafts. You can also monitor the progress of excavation work at the service.

A briefing for residents will be held at Iivisniemi School (Arttelikuja 4) on 10 March at 18.00–19.00, explaining about the project, building site arrangements and excavation.

We apologise for any inconvenience caused.

Further information:
Worksite hotline Lemminkäinen Infra Oy, tel. +358 400 753 317
Site Manager Harri Vehola, Lemminkäinen Infra Oy, tel. +358 40 750 8564
Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700

Open excavation to begin on Yläkartanonkuja in Soukka

The open excavation works of the Soukka station and rail tunnels will begin at the location of a technical shaft on Yläkartanonkuja. Work begins on 15 February.
Blasting for open excavation will be announced by a series of short signals before the blast and a long signal afterwards.

The monitoring service available on the Länsimetro website shows the rail line and the location of stations and shafts. You can also monitor the progress of excavation work at the service.
We apologise for any inconvenience caused.

Further information:
Skanska Infra Oy, responsible Site Manager Lauri Harri, lauri.harri(at)skanska.fi, worksite telephone +358 50 560 9092
Länsimetro feedback phone number (Mon-Fri 9 a.m.-3 p.m.), tel. +358 50 377 3700

Smoke extraction fans to be tested during the week beginning on 18 January

West metro smoke extraction fans will be tested during the week beginning on 18 January in all shafts from Ruoholahti to Mäntyviita in Tapiola. The tested fans will be switched on and operated at full speed for a maximum of one hour. The tests will be performed in the third week of January, starting on 19 January, on weekdays (Monday to Friday) between 08:00 and 16:00. During the test, a drone will be audible from the shaft. The sound will be stronger when the fans are operated at full speed. Dust may also be blown out from the shafts.

The shafts in which fans will be tested:
– Mäntyviita shaft in Tapiola
– Tekniikantie shaft in Otaniemi
– Otaranta shaft (at the end of Betonimiehenkuja)
– Keilalahti shaft (next to Microsoft)
– Karhusaari shaft
– Hanasaari shaft
– Katajaharju shaft
– Myllykallio shaft
– Lauttasaari shaft (at the corner of Pohjoiskaari and Lauttasaarentie)
– Salmisaari shaft

A total of 32 smoke exhaust fans have been installed in the Ruoholahti–Matinkylä section. In case of an emergency, the fans will be used for blowing smoke out through the shafts from underground facilities.

The first phase of Länsimetro to Matinkylä will open to traffic on 15 August 2016.

Further information:
Länsimetro feedback phone number (Mon-Fri 9 a.m.-3 p.m.), tel. +358 50 377 3700

Kalliorakennus-Yhtiöt won the Kivenlahti station and rail tunnel excavation contract

Kalliorakennus-Yhtiöt Oy has won the Kivenlahti station and rail tunnel excavation contract for Länsimetro’s Matinkylä–Kivenlahti section. Kalliorakennus will excavate the site of the Kivenlahti station, approximately 2 kilometres of parallel tunnels, a rail switching hall and the necessary shafts to the surface. This contract is worth EUR 26.3 million and work will begin in December.

– The excavation of the Matinkylä–Kivenlahti section continues with the excavation of stations and rail tunnels. The excavation works will continue until the end of 2017, says Matti Kokkinen, CEO of Länsimetro Oy.

The section from Matinkylä to Kivenlahti will be seven kilometres long and include the new stations of Finnoo, Kaitaa, Soukka, Espoonlahti and Kivenlahti. In addition, an underground metro depot will be constructed at Sammalvuori. The stretch will be opened to traffic in 2020. Traffic to Matinkylä will begin on 15 August 2016.

Further information:
Matti Kokkinen, CEO, Länsimetro Oy, tel. +358 50 347 1558, matti.kokkinen(at)lansimetro.fi

Water supply interruption in Tyskaksenkaari street 5-6 December 2015

Due to alterations in the main water pipeline, performed by excavation contractor Destia Oy along Tyskaksenkaari street, there will be a break in the water supply from 11.00 p.m on 5 December to 01.00 p.m. on 6 December.
We apologise for any inconvenience caused.

Further information:
Worksite hotline 040 637 5377
Site Manager Esa Juhantila, Destia Oy, esa.juhantila(at)destia.fi
Länsimetro feedback phone, Mon-Fri 9 a.m. to 3 p.m. +358 50 377 3700

Excavation for Kivenlahti metro station and rail tunnel to begin

The excavation for the Kivenlahti metro station and rail tunnel will begin soon, with Kalliorakennus-Yhtiöt Oy as the excavation contractor. The work will begin immediately after the completion of the excavation of the access tunnel during November and December. The Kivenlahti worksite area will expand, resulting in Kivenlahdentie to be closed for traffic between Kivenlahdenkatu and Merivirta as of 4 January 2016. An entrance to the station will be built on Kivenlahdentie. Car and bus traffic will be directed to an alternative route as seen in the attached map. There will be no bus traffic in the closed area. The bus stops on Kivenlahdenkatu and Merivirta will be in use as usual, and two new bus stops will be added along Merivirta. Pedestrian and cycle traffic on Kivenlahdentie will be directed around the worksite area. Merivirta will also be equipped with pedestrian crossing traffic lights.

Another entrance to the station, the Kivenlahdentori entrance, will be built on the site of the temporary dog park. Work on the site will begin with earthmoving. The dog park will be relocated west of the worksite area. The dog park will permanently move to Ruukinmäki in the summer of 2016.

These temporary traffic arrangements will remain in force until the construction process is complete, at least until 2020.

Working hours at the site, as determined by the Espoo Environment Institute, are as follows:
Earthwork and open excavation
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–22.00 and Sat 9.00–18.00)
Tunnel excavation (grout hole drilling, drilling, scaling)
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–7.00)
Blasting in the tunnel
• Mon–Fri 7.00–22.00 and Sat 9.00–18.00
Loading of excavated rock and transportation
• Mon–Fri 7.00–22.00 and weekends 9.00–22.00
• Mon–Fri 22.00–7.00 and weekends 22.00–9.00 if no disturbance is caused to the neighbourhood

Excavated rock will be taken to Länsiväylä and further afield for use in other construction projects. Haulage will be based on the blasting times. Blasting will occur 1–3 times a day. Excavation is estimated to continue until the end of 2017.

The monitoring service available on the Länsimetro website shows the rail line and the location of stations and shafts. You can also monitor the progress of excavation work at the service.

A briefing for residents will be held at Maininki School on 1 December at 19.00, explaining about the project, building site arrangements and excavation.
We apologise for any inconvenience caused.

Further information:
Länsimetro feedback phone number (Mon-Fri 9 a.m.-3 p.m.), tel. +358 50 377 3700
Kalliorakennus-Yhtiöt Oy, Site Manager Meeri Kaartinen, meeri.kaartinen@kalliorakennus
24-hour hotline for the site +358 50 342 2461

Kivenlahti työmaa