Environmental restoration beginning at Koivusaari worksite base

SRV Rakennus will be completing its work on the site by mid-November. What still remains to be done is the in-situ casting of the mouth of the access tunnel at Vaskisalmenkuja, and the routing and implementation of the pedestrian and bicycle paths leading to Hanasaarenranta.
Starting at the end of September, the base will be removed and the area restored to its original condition. The building site huts will be removed during the week beginning on 26 September 2016. The remaining work stages may cause temporary traffic arrangements.

Further information:
SRV Rakennus Oy, 24 h hotline tel. +358 40 631 3838
Reima Liikamaa, Site Manager +358 40 842 8368
Länsimetro feedback phone number (Mon–Fri 9.00–15.00) +358 50 377 3700