Excavation beginning on Soukantori station entrance

Two entrances will be constructed to the Soukka metro station, one at Soukantori and
another at Yläkartanontie. The demolition of a business wing is now ready at Soukantie 14, which had to be completed before excavating the Soukantori entrance.

The current work phases include open excavation and vibration isolation drilling, after which work will continue with the excavation of the shaft. This work is estimated to continue until the end of the year. The working hours for all phases of superstructure construction are Monday to Friday, 7.00 to 18.00. Blasting for open excavation will be announced by a series of short signals before the blast and a long signal afterwards.

We apologise for any inconvenience caused by the work.

Further information:
Skanska Infra Oy, responsible Site Manager Lauri Harri, lauri.harri(at)skanska.fi, worksite phone +358 50 560 9092
Länsimetro feedback phone number (Mon–Fri 9.00–15.00) +358 50 377 3700