Excavations near Maininkitie until the end of 2017

Excavation work in Espoonlahti to continue until the end of 2017

Rail tunnels of the West Metro’s second phase are being excavated in Espoonlahti. The rail tunnels to the west will be completed in August 2017 and the depot junctions and the Maininkitie shaft by the end of 2017.

In the near future, in early April 2017, superstructure construction work will begin at the Espoonlahdenkatu entrance. This work will also continue until the end of 2017. Excavation of the upper parts of the Maininkitie shaft and its collar structures will be completed in April–May 2017.

In addition to the metro worksite at Espoonlahti, other work under way in the area includes the construction of a shopping centre by Citycon Oyj and street construction by the City of Espoo. Information about these is available through their own communication channels.

Excavation work in Kivenlahti well under way

The last station of the West Metro’s second phase will be in Kivenlahti, where excavation work is well under way. The Kivenlahti tunnel’s eastern end, i.e. the affected area of Maininkitie, will be completed within approximately two months, after which bolt-boring will continue for around a month. The drilling work will be undertaken on weekdays from 7 a.m. to 6 p.m. and excavation blasting on weekdays before 10 p.m.

Excavation work at Kivenlahti station and its western end will continue until July–August.

The largest excavation work in Sammalvuori to be completed in June

As part of the West Metro’s second phase, an underground depot is being constructed in Sammalvuori. This night time depot for metro trains will also include maintenance facilities. Approximately half of the excavations for the connection rails have been done, and the aim is to complete the excavation of the largest masses by the end of June 2017. Blasting in Sammalvuori takes place on weekday mornings, usually around 7 a.m. to 9 a.m., and in the evenings from 7 p.m. to 10 p.m.  Occasional blasting work may take place at other times.

Excavation of the shaft for the Sammalvuori gate has now been completed next to the S-Market in Kivenlahti. The next step will be reinforcement work, to be followed by construction work. Fixed vibration measurement units have been placed extensively in the area, and more of these will be added if needed as the excavation work progresses.

Further information:

24-hour hotline for the Sammalvuori site: +358 50 343 7233

24-hour hotline for the Espoonlahti site: +358 40 637 5377

24-hour hotline for the Kivenlahti site: +358 50 342 2461

Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700

Excavated rock loaded in Sammalvuori on a new timetable

Excavated rock at west metro’s Sammalvuori depot site will be dumped, loaded and screened between 6 March and 30 June 2017 on a new timetable. The timetable has been adjusted.

The noise permit complied with states that excavated rock transported out of the tunnel may be dumped on the north-east side of the tunnel mouth at Sammalvuori metro depot on weekdays (Mon–Fri) at 7.30–22.00 and, if needed, on Saturdays at 9.00–18.00.

Excavated rock transported out and stored overground may be loaded on weekdays at 7.00–17.30, and screening of excavated rock is allowed on weekdays (Mon–Fri) at 8.00–17.30.

Furthermore, a noise embankment is being built on the edge of the site, and it is estimated to be completed by 18 March.

Further information:

24-hour hotline for the site, Sammalvuori consortium, tel. +358 50 343 7233

Site Manager Juha Selin, juha.selin@kalliorakennus.com
Länsimetro feedback phone number, Mon–Fri 9.00–15.00, tel. +358 50 377 3700

Helsinki City Rescue Department training at the Koivusaari station from 27 February to 2 March

The Helsinki City Rescue Department will train firefighting and personal rescue on 27 and 28 February and 1 March at the Koivusaari station, and on 2 March there and at the Katajaharju shaft. The training will take place from 11 am to 2 pm each day. The rescue exercises are part of the West Metro’s introduction into use.

The purpose of the training is to practice rescue missions using the West Metro’s security systems. This is also a cooperation exercise between various actors such as the Helsinki City Rescue Department and the Länsi-Uusimaa Department for Rescue Services, the Metro Control Room and other personnel of Helsinki City Transport (HKL), emergency care and the police.

During the training, several rescue vehicles will be parked around the Koivusaari station and nearby shafts. Theatrical smoke will be used in the exercise, and this may reach the surface near the training locations.

The Koivusaari station is located at the address Sotkatie 11. The Katajaharju shaft is at Isokaari 33.

Further information:

Jani Pitkänen, Fire Chief, Helsinki City Rescue Department, tel. +358 (0)50 433 6905

Excavation work for Sammalvuorenportti shaft begins

The actual excavation work at the Sammalvuori metro depot, i.e.  the Sammalvuorenportti shaft, will start in week 7. The shaft worksite area is located between Kivenlahdentie and Länsiväylä, close to the ABC service station. The excavation of the shaft will be carried out through the tunnel below. Work at the shaft began in October 2016 with the superstructure construction work followed by open excavation above ground.

Further information:

24-hour hotline for the site, Sammalvuori consortium, tel. +358 50 343 7233

Site Manager Juha Selin, juha.selin@kalliorakennus.com
Länsimetro feedback phone number (Mon–Fri 9.00–15.00) +358 50 377 3700

Summary of decisions 16 February 2017: The procurement strategy for the second phase was presented

The procurement strategy for the second phase of the West Metro project was presented to the Board of Länsimetro Oy at its meeting on 16 February 2017. The procurement strategy will take into account experiences from the first phase. The goals of the strategy include ensuring adequate competition and clear contract scoping. The procurement strategy will also emphasise dialogue between the different parties during the procurement phase and cooperation with the contractor during contract implementation. Länsimetro’s procurements will be announced in the public procurement system HILMA.

The report commissioned by the Board was presented to the Board. The Board will continue to discuss the matter in its next meeting in March.

The Board also approved Länsimetro Oy’s financial statement as well as a proposal that the organisation responsible for building the West Metro will move into shared premises during the spring.

The Board also approved a policy to draw up a summary of decisions made after every Board meeting. According to the City of Espoo’s corporate group guidelines, the City’s major subsidiaries must prepare a public summary of decisions made at Board meetings.

The next meeting will be held on 1 March 2017.

Further information:

Ville Saksi, MD, Länsimetro Oy, tel. +358 (0)40 823 2086

Olli Isotalo, Chairman of the Board of Länsimetro Oy, tel. +358 (0)50 593 3359

Media contacts: Satu Linkola,Communications Director, tel. +358 (0)46 877 3392