Smoke extraction fans to be tested

West metro smoke extraction fans will be tested in all shafts from Ruoholahti to Tiistilä in Matinkylä. The tested fans will be switched on and operated at full speed for a maximum of one hour. The tests will start running 26 April, on weekdays (Monday to Friday) between 08:00 and 16:00. During the test, a drone will be audible from the shaft. The sound will be stronger when the fans are operated at full speed. Dust may also be blown out from the shafts.

A total of 32 smoke exhaust fans have been installed in the Ruoholahti–Matinkylä section. In case of an emergency, the fans will be used for blowing smoke out through the shafts from underground facilities.

The first phase of Länsimetro to Matinkylä will open to traffic on 15 August 2016.

Further information:
Länsimetro feedback phone number (Mon-Fri 9 a.m.-3 p.m.), tel. +358 50 377 3700

Excavation work for Espoonlahti metro station and rail tunnels begins

The excavation for the Espoonlahti metro station and rail tunnels will begin soon, with a consortium established by Finnish company Destia Ltd and Czech company Metrostav a.s. as the excavation contractor. The consortium’s earlier contracts on Länsimetro’s Ruoholahti–Matinkylä section include the access tunnels of Lauttasaari and Koivusaari and a rail tunnel in Karhusaari. The works will commence in April. The excavation will include the Espoonlanti metro station, 1,470 metres of parallel tunnels, two exit shafts and the shafts connected to the station in the area of the present Lippulaiva shopping centre.

In connection with the project, part of Lippulaiva’s underground car park will be demolished. Before the demolition, the car park’s car washing area will be relocated. Furthermore, alterations will be made in Lippulaiva’s western yard area based on the shopping centre’s goods delivery needs.

Working hours at the site, as determined by the Espoo Environment Institute, are as follows:
Earthwork and open excavation
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–22.00 and Sat 9.00–18.00)
Tunnel excavation (grout hole drilling, drilling, scaling)
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–7.00 and weekends and mid-week holidays)
Blasting in the tunnel
• Mon–Fri 7.00–22.00 and Sat 9.00–18.00
Loading of excavated rock and transportation
• Mon–Fri 7.00–22.00 and weekends 9.00–22.00 (and if no disturbance is caused to people indoors, also Mon–Fri 22.00–7.00 and weekends and mid-week holidays)

Excavation is estimated to continue until the beginning of 2018. The Follow-up-service available on the Länsimetro website shows the rail line and the location of stations and emergency exit shafts. You can also monitor the progress of excavation work at the service.
A briefing for residents will be held at the auditorium of Storängens skola (Espoonlahdentie 10) on 25 April at 18.00, explaining about the project, building site arrangements and excavation.

We apologise for any inconvenience caused.

Further information:
Worksite hotline Destia Oy, tel. +358 40 637 5377
Esa Juhantila, Project Manager, tel. +358 400 539 302
Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700

The Destia/Metrostav consortium has won the Espoonlahti station and rail line excavation contract

The contract for the Espoonlahti station and rail line excavation works has been awarded to a consortium established by Finnish company Destia Ltd and Czech company Metrostav a.s. The works will commence in April 2016 and are due for completion at the beginning of 2018. The total value of the contract is approximately EUR 31.5 million. The excavation will include the Espoonlahti metro station, 1,470 metres of parallel tunnels, two exit shafts and the shafts connected to the station in the area of the present shopping centre.

“Excavation works are already under way at Kivenlahti, Soukka, Kaitaa and Finnoo stations and the rail line between them. Approximately 1.2 kilometres of the 14-kilometre tunnel has been excavated so far. Excavation of the Sammalvuori underground depot will begin later in the spring”, says Länsimetro Oy’s CEO Matti Kokkinen.

The section from Matinkylä to Kivenlahti will be seven kilometres long and include the new stations of Finnoo, Kaitaa, Soukka, Espoonlahti, and Kivenlahti. The line will open in 2020. Trains to Matinkylä will operate from 15 August 2016.

Further information:
Matti Kokkinen, CEO, Länsimetro Oy, tel. +358 50 347 1558, matti.kokkinen(at)ansimetro.fi

Länsimetro Oy is a company jointly owned by the Cities of Espoo and Helsinki, tasked with building the West Metro underground line. The Ruoholahti–Matinkylä section will open to the public in August 2016. Construction of the Matinkylä–Kivenlahti section is under way. This stretch will be completed in 2020.

SRV Infra wins contract for Kaitaa station and rail line excavation works

The contract for Kaitaa station and rail line excavation works has been awarded to SRV Infra Oy. The works will commence in April 2016 and are due to be completed by the end of 2017. The total value of the contract is approximately EUR 32 million. The contract covers excavation works at Kaitaa metro station, 1,600 metres of parallel tunnels, three separate shafts connected to the station, and exit shafts on Hyljetie and Riilahdentie.

– “Excavation works are already under way at Soukka, Kivenlahti and Finnoo stations and the rail line between them. Just over one kilometre of the 14-kilometre tunnel has been excavated so far. Excavation of the Sammalvuori underground depot and works in Espoonlahti will begin later in the spring”, says Länsimetro Oy’s CEO Matti Kokkinen.

The section from Matinkylä to Kivenlahti will be seven kilometres long and include the new stations of Finnoo, Kaitaa, Soukka, Espoonlahti, and Kivenlahti. In addition, an underground depot will be constructed at Sammalvuori. The line will open in 2020. Trains to Matinkylä will operate from 15 August 2016.

Further information:
Matti Kokkinen, CEO, Länsimetro Oy, tel. +358 50 347 1558, matti.kokkinen(at)lansimetro.fi
Länsimetro Oy is a company jointly owned by the Cities of Espoo and Helsinki, tasked with building the West Metro underground line. The Ruoholahti–Matinkylä section will open to the public in August 2016. Construction of the Matinkylä–Kivenlahti section is under way. This stretch will be completed in 2020.

Construction of metro entrances in Soukka

Two entrances will be constructed to the Soukka metro station, one on Soukantori and the other in Yläkartanontie. In connection with the excavation of the Soukantori entrance, a wing of a commercial building at Soukantie 14 will be demolished. The demolition, due to begin in July, is estimated to take four weeks. Another building by the so-called Puotitalo will be demolished in Yläkartanontie. This demolition will begin at a later date, to be announced in due course. The other entrance to Soukka station will be built in Yläkartanontie.

We apologise for any inconvenience caused.

Further information:
Skanska Infra Oy, responsible Site Manager Lauri Harri, lauri.harri(at)skanska.fi, worksite telephone +358 50 560 9092
Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700

Excavation work for Kaitaa metro station and rail tunnels begins

The excavation for the Kaitaa metro station and rail tunnels will begin soon, with SRV Infra Oy as the excavation contractor. The work will begin immediately after the completion of the excavation of the access tunnel in early April. The excavation will include the Kaitaa metro station, 1,600 metres of parallel tunnels, three separate shafts connected to the station and the Hyljetie and Riilahdentie exit shafts.

Working hours at the site, as determined by the Espoo Environment Department, are as follows:
Earthwork and open excavation
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–22.00 and Sat 9.00–18.00)
Tunnel excavation (grout hole drilling, drilling, scaling)
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–7.00 and weekends and mid-week holidays)
Blasting in the tunnel
• Mon–Fri 7.00–22.00 and Sat 9.00–18.00
Loading of excavated rock and transportation
• Mon–Fri 7.00–22.00 and weekends 9.00–22.00 (and if no disturbance is caused to people indoors, also Mon–Fri 22.00–7.00 and weekends and mid-week holidays)

Excavation is estimated to continue until the end of 2017. The monitoring service available on the Länsimetro website shows the rail line and the location of stations and emergency exit shafts. You can also monitor the progress of excavation work at the service.

A briefing for residents will be held at Kaitaa School (Iivisniementie 1) on 5 March at 18.00–19.00, explaining about the project, building site arrangements and excavation.

We apologise for any inconvenience caused.

 

Further information:

Worksite hotline SRV Infra Oy, tel. +358 400 459 827

Site Manager Risto Hast

Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700

Lemminkäinen has won the Finnoo station and rail line excavation contract

Lemminkäinen Infra Oy has won the Finnoo station and rail line excavation contract. Work begins in March 2016, and the contract is due for completion in October 2017. The total contract price is approximately EUR 36 million. In addition to the excavation of Finnoo station and rail tunnels, the contract covers the excavation of a new wastewater tunnel. All in all, 1,380 metres of new metro line and 771 metres of drain tunnels will be excavated.

– The excavation of Soukka and Kivenlahti stations and rail line is in progress. Excavation work is about to begin in Kaitaa and Finnoo and at the underground metro depot in Sammalvuori. Work in Espoonlahti will start later in the spring, says Matti Kokkinen, CEO of Länsimetro Oy.

The section from Matinkylä to Kivenlahti will be seven kilometres long and include the new stations of Finnoo, Kaitaa, Soukka, Espoonlahti and Kivenlahti. In addition, an underground metro depot will be constructed at Sammalvuori. The stretch will be opened to traffic in 2020. Traffic to Matinkylä will begin on 15 August 2016.

Further information:
Matti Kokkinen, CEO, Länsimetro Oy, tel. +358 50 347 1558, matti.kokkinen@lansimetro.fi

Länsimetro Oy is a company jointly owned by the Cities of Espoo and Helsinki, tasked with building the West Metro underground line. The Ruoholahti–Matinkylä section will open to the public in August 2016. Construction of the Matinkylä–Kivenlahti section is under way. This stretch will be completed in 2020.

Seven-year project to be completed in August

The eight stations and 14 kilometres of track to Matinkylä are due to open to the public on 15 August 2016. The excavation and building works have employed approximately 1,500 builders, and the total workload across the project will amount to approximately 4,500 person-years. The final cost estimate for the project is EUR 1,088 million. The project plan gave the cost of the project as EUR 713.6 million (at 2007 prices). Taking into account the rate of inflation, the cost estimate was EUR 848.0 million. The final cost of the project will therefore be EUR 240 million, or 28.3%, higher than planned.

Excavation works began in November 2009. The tunnels had been dug by February 2014, and the tracks had been laid by December 2015. In addition to new stations and two parallel rail tunnels, the project has involved building 15 vertical shafts for emergency exit, ventilation, pressure relief and smoke extraction purposes, nine sets of points, and a total of 54 cross passages between the twin tunnels. Passenger safety is ensured by the underground network’s 52 different automation systems. Safety is further reinforced by systems such as 32 smoke extractors, automatic smoke detection systems, fire extinguisher systems and fire escapes, as well as eight auxiliary power units. All the entrances to the underground are wheelchair accessible. There are a total of 46 lifts and 72 escalators in the underground.

The various systems will be tested independently, per station, and together during the spring. Trains will begin test runs in March. Once the line opens to the public, bus routes that previously terminated in Kamppi will be extended to provide a connecting service to Matinkylä and Tapiola according to a plan drawn up by Helsinki Region Transport. Underground trains will run more frequently than they do now. Two underground lines will be in operation: Matinkylä–Vuosaari and Tapiola–Mellunmäki. At peak times on weekdays, trains will run at 2.5-minute intervals on the section shared by both lines (Tapiola–Itäkeskus). Underground trains currently run at four-minute intervals during peak times.

Further information:
Matti Kokkinen, CEO, Länsimetro Oy, tel. +358 50 347 1558, matti.kokkinen@lansimetro.fi

Länsimetro Oy is a company jointly owned by the Cities of Espoo and Helsinki, tasked with building the West Metro underground line. The Ruoholahti–Matinkylä section will open to the public in August 2016. Construction of the Matinkylä–Kivenlahti section is under way. This stretch will be completed in 2020.

Picture gallery

Excavation work for Finnoo metro station and rail tunnels begins

The excavation for the Finnoo metro station and rail tunnels will begin soon, with Lemminkäinen Infra Oy as the excavation contractor. The work will begin immediately after the completion of the excavation of the access tunnel during March. The excavation will include the Finnoo metro station, 1,350 metres of parallel tunnels, two shafts connected to the station and the Suomenlahdentie shaft.

Additionally, short sections of the sewage tunnels leading to the Blominmäki wastewater treatment plant will be excavated at the same time, for the water services of the Helsinki Region Environmental Services Authority HSY.

Working hours at the site, as determined by the Espoo Environment Department, are as follows:
Earthwork and open excavation
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–22.00 and Sat 9.00–18.00)
Tunnel excavation (grout hole drilling, drilling, scaling)
• Mon–Fri 7.00–18.00 (and if no disturbance is caused to people indoors, also 18.00–7.00 and weekends and mid-week holidays)
Blasting in the tunnel
• Mon–Fri 7.00–22.00 and Sat 9.00–18.00
Loading of excavated rock and transportation
• Mon–Fri 7.00–22.00 and weekends 9.00–22.00 (and if no disturbance is caused to people indoors, also Mon–Fri 22.00–7.00 and weekends and mid-week holidays)

Excavation is estimated to continue until the end of 2017.

The follow-up service available on the Länsimetro website shows the rail line and the location of stations and emergency exit shafts. You can also monitor the progress of excavation work at the service.

A briefing for residents will be held at Iivisniemi School (Arttelikuja 4) on 10 March at 18.00–19.00, explaining about the project, building site arrangements and excavation.

We apologise for any inconvenience caused.

Further information:
Worksite hotline Lemminkäinen Infra Oy, tel. +358 400 753 317
Site Manager Harri Vehola, Lemminkäinen Infra Oy, tel. +358 40 750 8564
Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700

Open excavation to begin on Yläkartanonkuja in Soukka

The open excavation works of the Soukka station and rail tunnels will begin at the location of a technical shaft on Yläkartanonkuja. Work begins on 15 February.
Blasting for open excavation will be announced by a series of short signals before the blast and a long signal afterwards.

The monitoring service available on the Länsimetro website shows the rail line and the location of stations and shafts. You can also monitor the progress of excavation work at the service.
We apologise for any inconvenience caused.

Further information:
Skanska Infra Oy, responsible Site Manager Lauri Harri, lauri.harri(at)skanska.fi, worksite telephone +358 50 560 9092
Länsimetro feedback phone number (Mon-Fri 9 a.m.-3 p.m.), tel. +358 50 377 3700