Superstructure construction for eastern entrance of Kaitaa station begins

SRV Infra will begin superstructure construction for the eastern entrance of Kaitaa station in week 27. The work will begin with the redirection of traffic and the felling of trees in the worksite area. The worksite area will be fenced off and the topsoil will be removed, after which work will continue on pile planking and excavation. Open excavation will be performed in the area; first a shaft will be excavated through open excavation and then via the tunnel below. Signals will be sounded to warn about the open excavation. The open excavation phase will last 4 to 5 months.

The working hours for all phases of superstructure construction are Monday to Friday, 7.00 to 18.00.

We apologise for any inconvenience caused by the work.

Further information:
Site Manager in charge of shaft, John Uusipuro, SRV Infra Oy, tel. +358 440 330 658
Worksite hotline SRV Infra Oy, tel. +358 40 183 0090
Länsimetro feedback phone number (Mon–Fri 9.00–15.00), tel. +358 50 377 3700