The Project Manager submitted a status report on the construction and cost monitoring of the Matinkylä–Kivenlahti section to the Board through the war room’s monitoring view. Construction is progressing in line with the project plan’s risk-assessed schedule and budget.
Länsimetro Oy’s Technical Director presented the situation for the Matinkylä–Kivenlahti section’s commissioning plan. The commissioning plan is proceeding on schedule.
The Board of Directors authorised the CEO to sign an agreement on tasks related to the preparations for the commissioning of the Matinkylä–Kivenlahti section and the actual commissioning phase with HKL. The tasks are linked to control room services and test runs, among other things.
The Board of Directors approved Länsimetro Oy’s budget proposal for 2021.
Länsimetro Oy’s CFO presented the cost monitoring for the Matinkylä-Kivenlahti section. Construction is progressing in line with the project plan’s budget. The CFO also presented the schedule for the financial statements 2020.
The CEO presented Länsimetro Oy’s recruitments.
The next meeting of the Board of Directors will be held on 28 January 2021.
Further information:
Olli Isotalo, Chairman of the Board of Länsimetro Oy, tel. +358 (0)50 593 3359
Ville Saksi, CEO, Länsimetro Oy, tel. +358 (0)40 823 2086
Media contacts: Satu Linkola, Communications Director, tel. +358 (0)46 877 3392