Dismantling of worksite base and restoration of site

The remaining technical construction work at the Koivusaari site involves superstructure construction work at the worksite base and its vicinity. Cast-in-place work will be carried out at the entrance of the Vaskisalmenkuja access tunnel. In addition, the contract will involve re-routing the pedestrian and bicycle lanes leading to Hanasaarenranta.

The implementation of the pedestrian and bicycle lanes and the final water and sewer line works at the north/south end of Vaskisalmenkuja will start at the beginning of October. The work stages scheduled for weeks 40 to 43 will involve a lot of heavy traffic. The remaining work stages may cause temporary traffic arrangements.

The work by SRV Rakennus is scheduled to be completed by mid-November.