Concrete casting of walls for the Espoonlahdentori entrance continues on Monday, 18 March

Concrete casting at the Espoonlahdentori entrance of the Espoonlahti metro station started during the week of 10 March. This work phase marks the beginning of the construction of walls for the west entrance.

The work is scheduled to continue on Monday, 18 March, at 6.00 am and will be completed on Tuesday, 19 March, at 1.00 am at the latest. One similar concrete casting work phase will be carried out later in March. The casting work is a long process, and unfortunately late-night work cannot be avoided; due to the height and size of the structure, the pouring of concrete must be completed in one go.

The driving of concrete trucks and pumping of concrete may cause noise. We apologise for any inconvenience this work may cause.

Further information

Timo Nuutinen, Site Manager, Destia Oy: tel. 050 390 1126, timo.nuutinen(at)destia.fi

Länsimetro’s feedback line (Mon–Fri, 9 am to 3 pm): 050 377 3700