Metro rails installed up to Keilaniemi station

West metro construction is proceeding: installation of metro rails began in the second week of February. At present, the work has progressed from Ruoholahti to the Keilaniemi station. 80 per cent of concrete has been cast in stations and 92 per cent of the support wall elements at the sides of the tunnels are in place.

Follow the progress of construction at the follow-up service.