The cutting of the foundation drilling walls has been started at the eastern end, and the first piles have been cut down. Cutting was started on the Länsiväylä motorway side and it continues counterclockwise around the station. Temporary traffic arrangements have been made on Sotkatie for the duration of the cutting.
Work is proceeding in the tunnel with interior work. Steel frames are being installed in the metro platform area. Also, the installation of rail tracks has commenced and is progressing towards the Koivusaari station.
As a general rule, heavy vehicles leaving the construction site should pass through the Hanasaari junction. Large vehicles that cannot navigate the Hanasaari junction are to use Sotkatie.
150 construction experts are currently working at the site.
More information:
SRV Rakennus Oy, 24 h hotline tel. +358 040 631 3868
Reima Liikamaa, Site Manager +358 040 842 8368
Länsimetro feedback phone number (Mon-Fri 9 a.m.-3 p.m.), tel. +358 50 377 3700