Soukka

Soukka station and rail line were excavated by Skanska Infra Oy.

All other excavation work, except the Yläkartanontie entrance, has been completed. Excavation will be performed at the Yläkartontie entrance from early June. It is estimated that the extraction phase will last until the end of September, and the entire shaft will be completed by the end of October.

The construction work for the Soukka station and the railway tunnels will begin in 2018.

Site contact information:
Site address: Soukanväylä 7

Kalliorakennus-Yhtiöt Oy (excavation of the Yläkartontie entrance): Site Manager Meeri Kaartinen, tel. +358 (0)50-3411970, meeri.kaartinen(at)kalliorakennus.com

Further information on the worksite: West Metro feedback phone number (Mon–Fri 9.00–15.00): +358 50 377 3700

What are shafts and how are they excavated? Further information on shaft buildings.

Working hours as determined by the Finnish Environment Institute

Noise decision regarding excavation and sheeting in Soukka