Matinkylä-Kivenlahti

Espoo City Council addressed and approved an adjusted project plan for the Matinkylä–Kivenlahti section at its meeting on 19 March 2018. The adjusted cost estimate for phase two is EUR 1,159 million. The section will be handed over to the operator in 2023.

The second phase of the West Metro is proceeding within the budget stated in the project’s financing decision.

By April 2019, the accumulated costs amounted to EUR 430 million. Länsimetro Oy regularly reports on the progress of the project, the actual costs and any changes from what was forecasted to the City of Espoo. The cost estimate for the metro stations includes the excavation of the metro and service tunnels, as well as the construction contracts and HVAC and electricity work for the stations.

The cost estimate for the project plan is presented at the November 2017 value.

Cost estimate and actual costs (EUR) April 2019 

Cost estimate Actual cost
Finnoo 159 M 56 M
Kaitaa 131 M 50 M
Soukka 146 M 43 M
Espoonlahti 149 M 51 M
Sammalvuori 103 M 60 M
Kivenlahti 167 M 51 M
Park & ride facilities 75 M
Planning 81 M 75 M
Construction contracting 88 M 38 M
Project reserve 60 M
Project plan 1 159 M 423 M
Index adjustment 74 M
Financing 59 M 7 M
Total costs 1 292 M 430 M
Government subsidy – 260 M – 109 M
Project’s financing need 1 032 M 321 M

The cost estimate for the project plan is presented at the November 2017 value.