Ruoholahti - Lauttasaarensalmi

Excavation under the sea from Ruoholahti to Lauttasaari

The excavation contract executed through the Ruoholahti access tunnel consists of two 400-metre metro tunnels under the sea (Lauttasaarensalmi). The contractor is YIT Construction Ltd. Previously, two 800-metre rail tunnels and an access tunnel have been excavated between Ruoholahti metro station and the sea shore at Salmisaari, a total length of 1,900 m of tunnel.

Worksite
24 h hotline tel. 050 532 2600
Sami Tiisala, Site Manager, tel. 040 869 0819
Jouni Hyvärinen, Work Foreman, tel. 040 197 1999

Preliminary timetable
07/2011 - 06/2012 Metro tunnel excavation
07/2012 Contract completion

Worksite base
The worksite base for this contract is located under the Länsiväylä motorway bridge beside the Holiday Inn hotel, address: Salmisaarenkatu 7. Traffic has been temporarily rerouted near the working site area.

Working hours at Ruoholahti
Weekdays
Boring 24 h (noise level limits)
Blasting 07.00-22.00
Transports 24 h

Weekends
Work that does not exceed the maximum noise level limits is allowed on weekends.

Noise levels
Noise level means an average A-weighted sound pressure level (LAeq) during working hours.
- Night-time (weekdays plus weekend) < 30 dB (LAeq)
- Weekdays 18.00 - 22.00 < 40 dB (LAeq)
- Weekends and mid-week holidays 07.00 - 22.00 < 35 dB (LAeq)